A Milestone in Progress: The First Tank of Concrete for the Chimney Foundation of the SPIC Green Energy Baicheng Project Successfully Casted
Time:2026-05-27  Views:15

In early summer, construction sites in Baicheng, Jilin Province are adorned with fluttering flags and the roar of machinery. Recently, the first concrete pour for the chimney foundation of SPIC Green Energy's Baicheng 2×660 MW coal-fired power supply project was successfully completed, marking the official commencement of construction on this core structure of the provincial-level key energy initiative and laying a solid foundation for its subsequent efficient advancement.

981847ccb6bf50ca9e5a649e8244484b

At the construction site, the long arms of two pump trucks extended fully, continuously injecting concrete into the foundation reinforcement framework—as if infusing the project with vital "arterial blood." Workers collaborated efficiently with clearly defined roles, adhering strictly to standards throughout every phase—from pump truck operation and concrete vibration to quality monitoring—to ensure a safe, efficient, and high-quality pouring process. As a critical landmark structure of the power plant, the chimney's foundation quality directly impacts its overall safe and stable operation. The successful pouring of the first concrete tank marks a significant milestone in the project.

The chimney foundation was constructed using large-volume concrete technology. To address challenges such as significant day-night temperature fluctuations and the susceptibility to thermal cracks in the Baicheng region, the project team conducted proactive planning and implemented targeted measures: developing a specialized construction plan, optimizing the concrete mix ratio, installing a comprehensive temperature monitoring system with insulation and curing protocols, and conducting multiple rounds of technical briefings and safety training to ensure both construction quality and safety.

Since its commencement, the project team has consistently adhered to the principles of safety first, quality-oriented practices, green construction, and lean building methodologies. It has rigorously implemented safety responsibilities, strengthened quality control throughout the entire process, actively adopted innovative technologies, advanced techniques, and premium materials, and strived to deliver a model-quality benchmark project.

The successful completion of this milestone not only serves as a comprehensive validation of the preliminary preparatory work but also signals the official commencement of main structure construction. Moving forward, the project team will rigorously uphold the three critical control points—safety, quality, and schedule—while advancing the construction with unwavering determination to ensure early project commissioning and provide robust support for regional energy supply security.