The steel tube X column of the intercooling tower of Unit 1 of Xinjiang Heavy Energy Shitoumei 2 million kilowatt coal power project was successfully closed
Time:2024-01-24  Views:82

At 9:58 am on November 18, 2023, with the roar of machinery, the last steel tube X inclined pillar of the intercooling tower of Unit 1 of Xinjiang Heavy Energy Shitoumei 2 million kilowatt coal power project was completed in place.Thus, the steel tube X column and steel ring beam of the intercooling tower of Unit 1 of this project was successfully closed.


The X column of the intercooling tower of Unit 1 began to be lifted from October 20, 2023 to November 18, 2023, lasting 30 days. Affected by the local windy weather and sudden drop in temperature, the construction period was delayed by 6 days. The effective hoisting time was only 24 days, 15 days ahead of the planned construction period. During the hoisting process, under the strict supervision of the owner and the supervision unit, and drawing on the successful experience of similar projects of the company, the hoisting speed of X column was once again raised to a new height, which was highly recognized by the owner, the designer and the supervision unit.


The smooth closure of the steel tube X column of the intercooling tower of Unit 1 cannot be separated from the strong support of the company. This project is the first time for the company to try the steel tube X column in the construction site processing, successfully solved the problem of large transportation. Because the steel tube X column belongs to the three-dimensional space system, the detailed steel structure design was carried out at the early stage of processing. At the same time, through the planning of the production site and the layout optimization of the processing equipment, the resource utilization rate was improved, the processing progress was guaranteed, and the integrated management of processing, production and installation was realized.


Although there were many difficulties during the construction period, but under the strong support of the company's leaders and departments and the careful organization of the project manager, the project management personnel and the construction team never flinch, but fully develop the enterprise spirit of "unity and struggle, innovation and transcendence, strong and profitless, steady and enterprising". The next step is that the project department will be fully devoted to the hoisting work of the steel tube X column of the No.2 intercooled tower. Although the climate conditions are more harsh, we are convinced that we can devote ourselves to the work with the highest enthusiasm to achieve the annual goal of this project. Create favorable conditions for the construction of the upper wall of the intercooled tower after the year.