On November 30, the first successful grid-connected power transmission commissioning of the boost station of the wind farm project in Yutang Village, Wanshan District, Guizhou, and the full-capacity grid-connected power generation officially entered the countdown.
The installation of electrical installation equipment of the boost station began in mid-September 2023, mainly including transformer, GIS, SVG, outgoing frame, high and low voltage switch cabinet, and secondary screen cabinet installation and commissioning. During the installation process, the project department scientifically formulated the installation and commissioning plan, overall arrangement of the installation process, avoided the cross operation of civil engineering and equipment installation, actively overcame the impact of the local adverse climate, and successfully passed the acceptance of the third party and the power supply bureau.
This power back-transmission is a comprehensive inspection of the corresponding protection, automation, communication equipment installation and commissioning of the 110kV equipment of the boost station, and successfully opened the "green channel" of power transmission.
Next, the project department will pay attention to the construction quality under the premise of ensuring safe production, complete the subsequent construction tasks such as fan hoisting and unit grid connection with high standards and strict requirements, and reasonably allocate resources. Adhere to the enterprise spirit of unity and hard work, innovation and transcendence, steady and enterprising, and strive to complete the full-capacity grid-connection goal as soon as possible.