At 10:07am on October 10, 2022, with the deafening sound of firecrackers, Section 69 of the #4 cooling tower of the power generation project of Guangxi Wing Ji Steel Co., LTD., which was constructed by our company, was finished, marking the smooth capping of the #4 cooling tower, and also marking our important stage victory, laying a solid foundation for the subsequent construction.
The construction of the wall of #4 cooling tower began on July 19, 2022, and it took 83 days and nights to complete the capping. In the face of the strict schedule requirements of the general contractor, the project department closely focused on key lines and key nodes, did its best to organize and strengthen coordination, took measures such as working overtime and improving efficiency, organized and arranged the construction according to the goal of one section a day, and completed the schedule target on time, winning the full recognition and trust of the general contractor and the owner.
In the subsequent construction process, the project department will continue to keep the fighting spirit, try to catch up with the next node target, ensure the project performance on schedule, and wholeheartedly create high-quality projects with wisdom and sweat.