Company News

Position:Home > News

The first tank of concrete of Zhundong 2×660MW Power Plant Project of Xinjiang Juneng Investment Co., Ltd. was poured smoothly
Time:2023-02-01  Views:382

On October 20, 2022, at 9:46 PM, the foundation concrete of Column A of the main workshop project of Unit 2 of Zhundong 2×660MW Power Plant Project of Xinjiang Zhuneng Investment Co., Ltd. began to be poured, marking the official start of the construction of the main project and entering the stage of comprehensive construction.


The Zhundong 2×660MW Power Plant Project of Xinjiang Zhuneng Investment Co., Ltd. is located in Wucaiwan Industrial Park, Zhundong Economic and Technological Development Zone, Jimsar County, Changji Prefecture, Xinjiang Uygur Autonomous Region. Our company undertakes the construction of # 2 unit's main workshop, chemical water, hydraulic, boost station, ammonia (urea), road, floor, strip coal yard, # 2 cold tower and other construction projects. It is scheduled to be completed on February 25, 2025.


After winning the bid, faced with the characteristics of tight schedule and heavy tasks in the early stage of the node, coupled with the severe epidemic situation in Xinjiang, the whole Xinjiang was in a state of lockdown and control, making personnel organization and material procurement extremely difficult. The project department takes the attitude of rushing to start work, actively prepares for the project, systematically carries out the overall planning of the project, actively implements the allocation of resources, and promotes the preparatory work. In the process of construction management to fully carry forward the "hard work, overcome difficulties" style of work, careful arrangement of the construction plan, before the construction of the team to carry out a detailed and comprehensive safety, technical disclosure, to ensure the safety of construction.#2 The foundation excavation drawing of Column A of the main workshop will be presented on October 15th, 2022, excavated on 16th, and passed the tank inspection on 17th; The foundation drawings arrived on the 19th, and the foundation concrete was poured smoothly on the 20th. The owner fully affirmed the working style of the project department of our unit, and awarded the project Department 20,000 yuan.


In the next step, the project department will fully implement the company's requirements of standardized and refined management, carefully analyze the key points and difficulties of construction according to the schedule of Party A, actively organize personnel, materials and machinery, make a comprehensive layout and elaborate planning, emphasize safety, control cost, ensure quality and seize nodes, and devote itself to the project construction with a more energetic state. Ensure the early stage of the project node target completed on schedule, realize the project "unit immediately put into operation, that is, stable, that is, profitable, that is, reach the design value, safely achieve the safe construction" zero accident target ", create the national gold medal of quality engineering ".

1-1