The first wind turbine of 50MW wind power project of Tianrun Wuyang Runjin Wushui was successfully completed
Time:2024-01-18  Views:349

1-1


At 17:04 on September 7, 2023, the hoisting of the first wind turbine of the 50MW wind power project of Tianrun Wuyang Runjin Wushui was successfully completed, realizing the goal of "approval, commencement and first hoisting in the same year", and starting the first gun of the hoisting of Tianrun Wuyang Runjin Wushui project.



2-1


Before the hoisting operation, in order to ensure the safe, orderly and efficient lifting work, the project department actively coordinated the road transformation and transportation of large equipment to the site, organized the supervision and hoisting personnel to seriously discuss the operation plan, strictly conducted the safety technology disclosure, clarified the operation responsibilities, carefully analyzed the operation risks, formulated preventive measures, and made detailed and solid preparations for the hoisting operation.In the hoisting operation, the safety upgrade control measures were adopted. In the hoisting process, the owner's leaders and the project manager Qin Zhao stood by the whole process to supervise, to ensure the safe and smooth completion of the hoisting operation.


3-1


The successful completion of the hoisting of the first fan marks a key step in the construction of Tianrun Wuyang Runjin Wushui wind power project. Next, the project team will continue to give full play to its hardworking style, grasp the promotion with the momentum of take-off, grasp the implementation with the speed of running, control the construction safety, process and quality with high standards and strict requirements, and strive to achieve the goal of full-capacity grid-connected power generation in 2023.