Concrete pouring for the foundation of the first wind turbine of Tianrun Wuyang Runjin Wushui 50MW wind power project was completed successfully
Time:2023-07-30  Views:197

Starting at 17:07 on 17 July and ending at 8:00 on 18 July, after 15 hours of day and night work, the first turbine foundation concrete pouring of Tianrun Wuyang Ruijin Wushui 50MW wind power project was completed successfully.


1-1


Fan foundation pouring has continuity and must be completed at one time. In order to successfully complete the task of fan foundation pouring, during the construction process, the project department always carries out the construction with high standards and strict requirements, effectively guaranteeing the safety and quality of the construction, and all the members work overtime, and the construction personnel overcome the difficulties and work in shifts. All the members worked overtime, the construction staff overcame difficulties and worked in shifts. The management staff supervised the site overnight, and the project department took many measures to complete the pouring of the foundation of the first wind turbine as scheduled.


The completion of the first fan foundation pouring marks the project construction into a new stage, providing a strong guarantee for the subsequent construction. In the next step, Tianrun Wuyang Runjin Wushui 50MW wind power project will make persistent efforts to achieve the company's strategic goals!


2-1