First wind turbine foundation pouring successfully completed for Yuanyang Runyuan 100MW wind power project
Time:2023-07-21  Views:263

At 17:00 on June 07, 2023, the concrete pouring of the first fan foundation of the Yuanyang Runyuan 100MW wind power project was successfully completed, marking the entry of the project into the assertive phase of fan foundation construction.


The project adopts pile foundation, the foundation pile is infill pile, the bearing platform is round bearing platform, the foundation diameter is 20 meters, the platform low elevation is -3.9/5.4 meters, the amount of steel reinforcement is 86.87 tons, the amount of foundation concrete is 651 cubic meters, the strength grade of foundation concrete is C40, the seepage resistance grade is P6, the frost resistance grade is F100.

1-1


Fan foundation pouring is continuous and must be completed in one pour. In order to successfully complete the task of the fan foundation pouring, during the construction process, the project department always takes high standards and strict requirements for construction, effectively guaranteeing construction safety and quality, all members worked overtime, and construction personnel overcame fatigue and took shifts. Starting from 2:00 am on June 7, 15 hours of continuous pouring, management personnel on-site overnight supervision, the project department took multiple measures and finally completed the first fan foundation pouring on schedule.

2-1

The completion of the pouring of the first wind turbine foundation marks the new stage of the project construction and provides a strong guarantee for the subsequent construction. In the next step, the Yuanyang Runyuan 100MW wind power project will continue to work hard to achieve the annual target of the project!